Contracts in progress
At present Centrum Projektowe is performing , among others: • technical documentation for building permit for erection of 2 power units in Opole Power Plant, • technical documentation of fuel system & infrastructure modernization for K8 boiler in PKN Orlen Power Plant, • technical documentation of new power unit (50 MWe / 150 MWt) for Bielsko-Biała CHP Plant, including: • fluidized bed boiler, • back pressure turbine, • 2 peak load boilers, • heat storage, • technical documentation for building permit for installation of saline water concentration for Organika Sarzyna Chemical Works, • installation for the production of insoluble sulfur in carbon disulfide plant (turnkey system, capacity 5000 t/y) for Siarkopol. |
|
|
|
|